Refurbishment of Toll Milling Plant on Track

by admin April 30, 2025
April 30, 2025

Challenger Gold Limited (ASX: CEL) (“CEL” the “Company”) notes the ASX Release by Austral Gold Limited titled ‘Austral Gold Provides Update on Casposo Plant Refurbishment’ today. The release provides an update on the refurbishment of the Casposo Processing Plant and reports that the refurbishment is on track for the start up of commercial operations in the second half of 2025.

HIGHLIGHTS

  • Austral Gold announced that Casposo Plant refurbishment is advancing safely and efficiently across all core workstreams.
  • Austral update aligns with second independent plant inspection commissioned by CEL.
  • CEL’s inspection was undertaken by the same process engineers that completed the Audit of the Casposo Plant and Restart Plan in December 2024.
  • Key takeaways from the second inspection report commissioned by CEL are:
    • Robust advancement across all key processing areas
    • Progress in line with existing refurbishment schedule
    • Solid-liquid separation capacity (previously identified as a key risk) appears adequate for the required 1000 TPD capacity
    • Sufficient time remaining to complete all maintenance work to meet the commissioning target in Toll Milling Agreement during the second half of 2025.

The Austral update aligns with a second independent plant independent inspection report received by the Company during April 2025. This report was prepared by the leading process group that completed the independent Audit of the Casposo Plant in December 2024 (ASX Release dated 13 December 2024).

Background to Toll Milling

The Company has executed a binding Agreement with Casposo Argentina Mining Limited, the operator of the Casposo Plant located in San Juan Argentina. This Toll Milling Agreement secures processing of a minimum of 450,000t of near surface Hualilan mineralised material over 3 years (ASX Release dated 30 December 2024).

The Casposo Plant, located 170km from Hualilan via established roads, has historically produced over 323,000 ounces of gold and 13.2 million ounces of silver. During operations, the plant achieved average annual production of 40,000 ounces of gold and 1.6 million ounces of silver at recoveries of 90% for gold and 79% for silver. The plant has been on care and maintenance.

The primary objective of this Toll Milling strategy is to capitalise on the current high gold price (above US$3,300/oz) to generate early cash flow. This cashflow will be allocated towards the construction of the standalone Hualilan Gold project including a Flotation with Tails Leach (“FTL”) circuit, a potential Heap Leach (“HL”) pad at Hualilan, and open pit mining fleet.

Click here for the full ASX Release

This post appeared first on investingnews.com

previous post
Trading Halt
next post
First Assay Results from Rae Copper Project Returns High Grade Copper

Related Posts

Uranium Price 2025 Year-End Review

December 10, 2025

Copper Price Forecast: Top Trends for Copper in...

December 10, 2025

Sankamap Metals

December 10, 2025

Prismo Metals Announces Continuance into British Columbia

December 9, 2025

Sandstone exploration drilling returns 157m @ 1.13g/t Au

December 9, 2025

Clem Chambers: Silver Can “Easily” Hit US$100, Retail...

December 9, 2025







    Stay updated with the latest news, exclusive offers, and special promotions. Sign up now and be the first to know! As a member, you'll receive curated content, insider tips, and invitations to exclusive events. Don't miss out on being part of something special.


    By opting in you agree to receive emails from us and our affiliates. Your information is secure and your privacy is protected.




    Recent Posts

    • Mamdani will introduce British antisemitism, taxes to US: Former UK prime minister

      December 10, 2025
    • China sharpens confrontation with Japan following reported radar run-in

      December 10, 2025
    • European talks reshape Ukraine’s peace plan as Zelenskyy refuses territorial concessions

      December 10, 2025
    • Senate Republicans land on Obamacare fix, tee up dueling vote with Dems

      December 10, 2025
    • Jim Caviezel starring in Bolsonaro biopic as son of jailed former president launches 2026 campaign

      December 10, 2025
    • About us
    • Contact us
    • Privacy Policy
    • Terms & Conditions

    Copyright © 2025 timeandsalesreporter.com | All Rights Reserved

    Time And Sales Reporter
    • World News
    • Politics
    • Stock
    • Investing
    • Editor’s Pick

    Read alsox

    Top 5 Canadian Cobalt Stocks of 2025

    November 1, 2025

    Allied Critical Metals Announces Corporate Update

    May 17, 2025

    The Chilling Effect: How Fear Drives Doctors Away...

    February 25, 2025