Refurbishment of Toll Milling Plant on Track

by admin April 30, 2025
April 30, 2025

Challenger Gold Limited (ASX: CEL) (“CEL” the “Company”) notes the ASX Release by Austral Gold Limited titled ‘Austral Gold Provides Update on Casposo Plant Refurbishment’ today. The release provides an update on the refurbishment of the Casposo Processing Plant and reports that the refurbishment is on track for the start up of commercial operations in the second half of 2025.

HIGHLIGHTS

  • Austral Gold announced that Casposo Plant refurbishment is advancing safely and efficiently across all core workstreams.
  • Austral update aligns with second independent plant inspection commissioned by CEL.
  • CEL’s inspection was undertaken by the same process engineers that completed the Audit of the Casposo Plant and Restart Plan in December 2024.
  • Key takeaways from the second inspection report commissioned by CEL are:
    • Robust advancement across all key processing areas
    • Progress in line with existing refurbishment schedule
    • Solid-liquid separation capacity (previously identified as a key risk) appears adequate for the required 1000 TPD capacity
    • Sufficient time remaining to complete all maintenance work to meet the commissioning target in Toll Milling Agreement during the second half of 2025.

The Austral update aligns with a second independent plant independent inspection report received by the Company during April 2025. This report was prepared by the leading process group that completed the independent Audit of the Casposo Plant in December 2024 (ASX Release dated 13 December 2024).

Background to Toll Milling

The Company has executed a binding Agreement with Casposo Argentina Mining Limited, the operator of the Casposo Plant located in San Juan Argentina. This Toll Milling Agreement secures processing of a minimum of 450,000t of near surface Hualilan mineralised material over 3 years (ASX Release dated 30 December 2024).

The Casposo Plant, located 170km from Hualilan via established roads, has historically produced over 323,000 ounces of gold and 13.2 million ounces of silver. During operations, the plant achieved average annual production of 40,000 ounces of gold and 1.6 million ounces of silver at recoveries of 90% for gold and 79% for silver. The plant has been on care and maintenance.

The primary objective of this Toll Milling strategy is to capitalise on the current high gold price (above US$3,300/oz) to generate early cash flow. This cashflow will be allocated towards the construction of the standalone Hualilan Gold project including a Flotation with Tails Leach (“FTL”) circuit, a potential Heap Leach (“HL”) pad at Hualilan, and open pit mining fleet.

Click here for the full ASX Release

This post appeared first on investingnews.com

previous post
On air, ’60 Minutes’ reporter says ‘none of us is happy’ about changes that led top producer to quit
next post
First Assay Results from Rae Copper Project Returns High Grade Copper

Related Posts

Hudbay Secures US$600 Million Mitsubishi Partnership for Arizona...

August 15, 2025

Allied Critical Metals Closes First Tranche of Oversubscribed...

August 15, 2025

Harvest Gold Kicks Off Drilling at Mosseau, Launches...

August 15, 2025

Horn Island Mining Lease Application Registered

August 15, 2025

Q2 2025 Interim Financial Statements

August 15, 2025

Zinc Stocks: 4 Biggest Canadian Companies in 2025

August 14, 2025







    Stay updated with the latest news, exclusive offers, and special promotions. Sign up now and be the first to know! As a member, you'll receive curated content, insider tips, and invitations to exclusive events. Don't miss out on being part of something special.


    By opting in you agree to receive emails from us and our affiliates. Your information is secure and your privacy is protected.




    Recent Posts

    • Ulta and Target will end deal for in-store beauty shops next year

      August 15, 2025
    • The CEO in chief: How Trump is getting what he wants from big business

      August 15, 2025
    • Social Security is 90 years old. We are making it smarter, better, faster under Trump

      August 15, 2025
    • Trump admin unveils groundbreaking tool ‘supercharging’ gov’t efficiency to ‘win the race’ for AI dominance

      August 15, 2025
    • Armenia and Azerbaijan leaders seek to ease Russian and Iranian concerns after US-brokered peace deal

      August 15, 2025
    • About us
    • Contact us
    • Privacy Policy
    • Terms & Conditions

    Copyright © 2025 timeandsalesreporter.com | All Rights Reserved

    Time And Sales Reporter
    • World News
    • Politics
    • Stock
    • Investing
    • Editor’s Pick

    Read alsox

    Trump Keeps Defying Established Law—What’s Up With That?

    February 3, 2025

    Sranan Gold Trenching Encounters 36.7 Grams/Tonne Gold over...

    August 8, 2025

    Crypto Market Recap: Bitcoin Price Stalls as Fed...

    June 21, 2025