Refurbishment of Toll Milling Plant on Track

by admin April 30, 2025
April 30, 2025

Challenger Gold Limited (ASX: CEL) (“CEL” the “Company”) notes the ASX Release by Austral Gold Limited titled ‘Austral Gold Provides Update on Casposo Plant Refurbishment’ today. The release provides an update on the refurbishment of the Casposo Processing Plant and reports that the refurbishment is on track for the start up of commercial operations in the second half of 2025.

HIGHLIGHTS

  • Austral Gold announced that Casposo Plant refurbishment is advancing safely and efficiently across all core workstreams.
  • Austral update aligns with second independent plant inspection commissioned by CEL.
  • CEL’s inspection was undertaken by the same process engineers that completed the Audit of the Casposo Plant and Restart Plan in December 2024.
  • Key takeaways from the second inspection report commissioned by CEL are:
    • Robust advancement across all key processing areas
    • Progress in line with existing refurbishment schedule
    • Solid-liquid separation capacity (previously identified as a key risk) appears adequate for the required 1000 TPD capacity
    • Sufficient time remaining to complete all maintenance work to meet the commissioning target in Toll Milling Agreement during the second half of 2025.

The Austral update aligns with a second independent plant independent inspection report received by the Company during April 2025. This report was prepared by the leading process group that completed the independent Audit of the Casposo Plant in December 2024 (ASX Release dated 13 December 2024).

Background to Toll Milling

The Company has executed a binding Agreement with Casposo Argentina Mining Limited, the operator of the Casposo Plant located in San Juan Argentina. This Toll Milling Agreement secures processing of a minimum of 450,000t of near surface Hualilan mineralised material over 3 years (ASX Release dated 30 December 2024).

The Casposo Plant, located 170km from Hualilan via established roads, has historically produced over 323,000 ounces of gold and 13.2 million ounces of silver. During operations, the plant achieved average annual production of 40,000 ounces of gold and 1.6 million ounces of silver at recoveries of 90% for gold and 79% for silver. The plant has been on care and maintenance.

The primary objective of this Toll Milling strategy is to capitalise on the current high gold price (above US$3,300/oz) to generate early cash flow. This cashflow will be allocated towards the construction of the standalone Hualilan Gold project including a Flotation with Tails Leach (“FTL”) circuit, a potential Heap Leach (“HL”) pad at Hualilan, and open pit mining fleet.

Click here for the full ASX Release

This post appeared first on investingnews.com

previous post
On air, ’60 Minutes’ reporter says ‘none of us is happy’ about changes that led top producer to quit
next post
First Assay Results from Rae Copper Project Returns High Grade Copper

Related Posts

Gold’s Meteoric Rise: Can the Price Break US$4,000...

October 2, 2025

Syntheia Closes Call Center Guys Acquisition

October 2, 2025

Lo Herma Resource Drilling Timing Confirmed

October 2, 2025

COB: Repayment of Promissory Note

October 2, 2025

Locksley Resources LimitedAssessment and Evaluation of DeepSolv Program...

October 1, 2025

Rua Gold

October 1, 2025







    Stay updated with the latest news, exclusive offers, and special promotions. Sign up now and be the first to know! As a member, you'll receive curated content, insider tips, and invitations to exclusive events. Don't miss out on being part of something special.


    By opting in you agree to receive emails from us and our affiliates. Your information is secure and your privacy is protected.




    Recent Posts

    • Charlie Javice sentenced to 7 years in prison for fraudulent $175M sale of aid startup

      October 2, 2025
    • YouTube to pay $24 million to settle Trump lawsuit

      October 2, 2025
    • Johnson accuses Schumer of blocking ‘real discussion’ to keep government open

      October 2, 2025
    • Trump remains open to talks with Kim Jong Un as South Korea warns of North Korean missile reach

      October 2, 2025
    • First bipartisan shutdown negotiations surface on Capitol Hill after funding bill blocked again

      October 2, 2025
    • About us
    • Contact us
    • Privacy Policy
    • Terms & Conditions

    Copyright © 2025 timeandsalesreporter.com | All Rights Reserved

    Time And Sales Reporter
    • World News
    • Politics
    • Stock
    • Investing
    • Editor’s Pick

    Read alsox

    Cato Tax Bootcamp: An International Tax Primer

    February 4, 2025

    Brunswick Exploration Announces AGM Results

    June 14, 2025

    Altech – Commences Selling Sodium Nickel Chloride Batteries

    September 30, 2025